The following rules of operation will be applied
to all developers during the development of the site.
GENERAL DUTIES
All staff employed in connection with the development of the site
will have due regard to the occupants of nearby dwellings in he
performance of their duties. All employees will be made aware of
these rules and will be bound by them.
WORKING HOURS
All activity connection with the normal working of the development
will occur between the hours of 07 .30 - 18.00 hours Monday to Friday,
07 .30- 13.00 hours on Saturdays. No works shall occur on Sundays
or Bank Holidays. Any exceptions to the above will require express
approval by the Cambourne Company Management. However, nothing herein
shall have the effect of restricting the use of completed houses
for sales purposes or operations necessary in the event of emergency.
Update - Quote the policy code when complaining
"Policy NE/15 of the adopted Local Development Framework 2007"
SITE ACCESS
The site will be accessed via roundabouts to be built on the A428
from the commencement of the development.
Construction traffic will be separated from sales traffic and residents
traffic at the first roundabout off the A428. No site traffic will
be permitted on the main site roads or adopted roads.
All construction traffic will be routed to the site in accordance
with the planning consent. That is, it will be directed to the site
via the main roads A428, A 14, Ml I, A5O5, A6O4 and the Caxton By-pass
when constructed.
Signage will be sited in the locality of the site and around the
local villages which directs the traffic via the main roads specified
above and away from the following villages;Bourn, Caxton, Comberton,
Coton. Toft, Hardwick, Highfields. Madingley, Dry Drayton, Knapwell
and Elsworth.
All developers are to apply, as a precondition of any contract,
restrictions on contractors and employees in respect of the access
arrangements above. Site Management will have the right, as a precondition
of granting any developer or contractor the opportunity to develop
any part of the site. to insist that operatives who act in a manner
which contravenes this rile will be removed from the contract.
SITE SECURITY ARRANGEMENTS
Staff will be employed to control access to the development.
Responsibility for individual development site security will lie
with the respective developer.
Signs will be utilised throughout the site to alert all concerned
where construction activities affect or occurs close to private
residences and public rights of way.
It is a requirement of health and Safety Regulations that all developments
require an appointed Safety Officer. This will be the responsibility
of each developer and contractor.
SITING OF OFFICES COMPOUNDS
All storage of materials and administrative accommodation situated
on the site of construction, shall be screened from adjacent activities
by close boarding, fencing or other boardjng. They should not be
situated adjacent properties which are already completed and occupied.
A series of common contractors car parks will be identified throughout
the development by the Cambourne Company and should be used by all
personnel associated with building activities.
No contractors vehicles will be permitted to be parked on spine
roads at any time.
CLEANING OF PUBLIC ROADS
The Cambourne Company will ensure that all adopted roads will be
cleaned at regular intervals daily in response to weather conditions.
The cost of this will be borne by all developers.
HAUL ROUTES
A series of dedicated haul routes will be identified throughout
the development which will be constructed to base course standard
do as to reduce the likelihood of nuisance caused from dust. These
will include the provision of wheel washing facilities, which will
be used on all vehicles leaving the site and entering the strategic
road network. The cost of this will be borne by all developers.
CONTROL OF WASTE
No disposal of waste materials shall occur within individual sites
through combustion or burying. All developers and contractors are
to ensure the regular removal of all waste from their sites. All
sites to be maintained in a clean and orderly manner throughout
construction.
Top soil/Soi1 stripping and movement
All top soil stripped from the site will be retained within the
site and either stored or re-spread in areas to be defined progressively
throughout the development.
SITE SIGNAGE
A strategic policy will be established prior to the commencement
of development to manage the use of temporary signs associated with
the development.
This will develop the principle that all signage will be accommodated
within one of a series of specially designed 'Cambourne' signs.
No individual developer boards, flags or other insignia will be
permitted in Cambourne or within individual development sites unless
exceptional circumstances can be demonstrated to the Cambourne company.
Construction traffic will be directed to
and into the site by complementary though distinct 'Cambourne' signs.
Sales signs will be incorporated into the
overall strategy for the whole development and will be the same
as normal Cambourne signs
|